NASA watchdog says the outlook isn’t good for its mega-moon rocket launcher

The NASA Office of Inspector General (OIG) published its report on the agency’s management of a second mobile launch tower for the space launch system (SLS) mega-moon rocket—and the forecast isn’t looking good. Right now, the OIG anticipates that the project will cost more than twice what was originally budgeted and will be completed roughly 2.5 years behind schedule.

Some Quick background

In order to launch SLS, the giant moon rocket NASA has been developing since 2011, the agency needs the ground infrastructure to support it. The mobile launcher consists of a ground platform that can withstand the blast from the rocket’s engines as it takes off. The launch tower and its many arms provide the rocket with all manner of necessary launch components, including power, fuel, remote monitoring, and communication with mission control.

The ML-2 contract

The first mobile launch tower for SLS, which is currently on the pad awaiting its wet dress rehearsal, was completed in 2010. In 2019, NASA awarded Bechtel National a $383M contract to build ML-2, a second launch tower for later, larger iterations of SLS.

Bechtel originally planned to complete construction on the tower by March 2023. So far, construction on the tower has not begun.

Bottom line up front

The tower is going to be late, over budget, and too heavy. 

The OIG report concluded that Bechtel’s poor performance caused 70% of the cost overruns and 1.5 years of project delays. The project had already cost NASA $436M by March 2022; it’s expected to cost $960M when all is said and done. 

The OIG report estimates that delivery won’t be until October 2025 at the earliest, which would delay Artemis IV, the second crewed flight of NASA’s Artemis program to return humans to the lunar surface, to no earlier than 2026. The culprits: underestimating the scope of the project, staff retention issues, and design flaws.

Bechtel came back with a statement (hat tip to Eric Berger) challenging the finding that its poor performance was to blame. Its argument: the OIG report ignored the impacts of the pandemic and unexpected design changes.

These numbers are what the OIG report sees as a best-case scenario. An independent review team analysis found that the project will most likely cost in the ballpark of $1.5B, with delivery in 2027 and Artemis IV thus delayed to 2028. 

Though the review primarily blames Bechtel, NASA isn’t off the hook, either. The agency awarded the ML-2 contract before it had finalized the design for the Exploration Upper Stage, leading to design changes during the contract period. It also didn’t follow an OIG recommendation from March 2020 to create separate project guidelines for the ML-2 contract.

Recommendations

The OIG urged NASA to take “corrective action” to speed up the project, but at this point, there’s not much to be done. NASA leadership is reportedly considering moving to a fixed-price contract for the rest of the project, but haven’t yet reached an agreement.

This story originally appeared on Payload, and is republished here with permission. 

https://www.fastcompany.com/90761162/nasa-watchdogs-says-the-mega-moon-rockets-outlook-doesnt-look-good?partner=rss&utm_source=rss&utm_medium=feed&utm_campaign=rss+fastcompany&utm_content=rss

Létrehozva 3y | 2022. jún. 16. 4:20:42


Jelentkezéshez jelentkezzen be

EGYÉB POSTS Ebben a csoportban

PBS chief Paula Kerger warns public broadcasting could collapse in small communities if Congress strips federal funding

As Congress moves to make massive cuts to public broadcasting this week, Paula Kerger, president and CEO of the Public Broadcasting Service (PBS), gives an unflinching look at the organization’s f

2025. júl. 9. 14:30:04 | Fast company - tech
These personality types are most likely to cheat using AI

As recent graduates proudly showcase their use of ChatGPT for final projects, some may wonder: What kind of person turns to

2025. júl. 9. 14:30:04 | Fast company - tech
Samsung fixed everything you hated about foldable phones—except the price

Just over a month ago, Samsung did something strange to start hyping up its next foldable phone announcements.

Those phones, which Samsung revealed today, are officially called the Samsu

2025. júl. 9. 14:30:04 | Fast company - tech
Tesla stock is tanking. Could shareholders fire Elon Musk?

It’s not a great time to be a Tesla shareholder. While the stock was up 2.5% in midday trading on Tuesday, July 8, it remains down for the month and has

2025. júl. 9. 12:10:05 | Fast company - tech
‘The /r/overemployed king’: A serial moonlighter was exposed for holding 19 jobs at Silicon Valley startups

A software engineer became X’s main character last week after being outed as a serial moonlighter at multiple Silicon Valley startups.

“PSA: there’s a guy named Soham Parekh (in India) w

2025. júl. 8. 22:20:04 | Fast company - tech
Texas flood recovery efforts face an unexpected obstacle: drones

The flash floods that have devastated Texas are already a difficult crisis to manage. More than 100 people are confirmed dead

2025. júl. 8. 17:40:02 | Fast company - tech